Prior to the installation: Pro Star provided a rental chiller and hooked it up to the building. Next the electrical sub-panel was replaced along with new wiring laid between the main panel and sub-panel. Next, we redesigned the piping layout and replaced both chiller pumps. Now we were ready to install the new 145 ton chiller.
Managing the work flow: The new chiller was up and running by the end of the second day. Our crew worked tirelessly and the project manager ensured on-going communication with ownership. Included in the install was a one-year service plan on the new unit.